Work on SPARK Programme to begin in the Corporate Area this week


Press Release From The Ministry of Economic Growth and Job Creation - 20250204

Work is scheduled to begin in the Corporate Area this week, under Work Order 1 of the  Shared Prosperity through Accelerated Improvement to our Road Network (SPARK) Programme.

Minister without Portfolio in the Ministry of Economic Growth and Job Creation, Hon. Robert Morgan, gave an update on the Programme to the House of Representatives this afternoon (Tuesday, February 4, 2025.

We have Everest Drive which started already. Then we’re going to have Bellevue Avenue in Kingston East and Port Royal.  In Kingston Western, we’re starting Bustamante Highway, (and) North Street from King Street to Crab Ground.  In St. Andrew East Rural we’re starting Passion Gardens and Bayview Retreat.  In St. Andrew Eastern, we’re doing Buttercup Drive, (and) Dougherty Drive. In St. Andrew North-Eastern, (we’re doing)  Liguanea Avenue and Richings Avenue;  St Andrew North-Central, Upper Aries and Orange Grove Road”, he stated.

He noted that Work Order 1 will be carried out at a cost of J$1.911 billion and will span 21 constituencies across eight (8) parishes, with a number of rehabilitation projects starting in several constituencies including the Corporate Area.

Minister Morgan said other roads to receive attention under Work Order 1 are located in South-Eastern, Eastern,  East-Central and South Central St. Catherine; North-West and Central Manchester; South-West, South East and North-East St. Elizabeth; Eastern and Western Portland; Central St. Mary; as well as Northern and Southern Trelawny, adding that  “we are actively assessing other additional roads to commence in the coming weeks”.

Work Order 2, he noted will cover 42 additional roads across 21 constituencies and is expected to commence in late February, while Work Order 3 which comprises another 42 roads across 21 additional constituencies, is scheduled to begin in early March.

The Minister stated that in this financial year, work will begin on about 126 critical roadways across Jamaica. 

“At the end, all constituencies will get an initial two SPARK roads before the end of the financial year. We expect that by April we will start seeing the completion of our first set of SPARK roads with this tranche and we expect that these three work orders will be completed by June of this year”, he stated.

Minister Morgan stated that to ensure accountability and efficiency, the Ministry of Economic Growth and Job Creation will strictly oversee project timelines, contractor performance and quality standards. 

He encouraged Members of Parliament and local stakeholders to remain engaged in the monitoring process to ensure that all communities benefit fully from this initiative.

“This is the next chapter of Jamaica’s development. With the SPARK Programme, we are not just fixing roads. We are building pathways of opportunity. This initiative is an investment in the future of our citizens and a demonstration of the Government’s unwavering commitment to national development”, he ended.

Click to watch the video.


Editor:

Remember to check our calendar to see what events are taking place this week. If you are aware of an event that will take place, send me a copy of the flier. Ensure that the organizers contact information is on the flier.

Click on the icon below to see the calendar:

Click to view the calendar.


_____________________________




Subscribe Now!

Remember that Bark Di Trute could fail to bark one day without your support. Send your ideas, stories, and news by WhatsApp at (876) 816-5261.




__________________________


________________________


2 comments:

  1. Full time the roads r long over due😁

    ReplyDelete
  2. Beg unu try fix Top Alston in Clarendon no road is there a beg ooo

    ReplyDelete

Blogs will be forwarded to national leaders, business leaders and others who might need to see such blogs.

Most Popular Post.